CONTRACT – construction – design and construct contract – contractor claimed additional payment for works required pursuant to development consent – whether works were “Excluded Works” – significance of definition commencing “Notwithstanding any other clause” – significance of grammatical meaning of clause – clause required to be read as a whole, harmoniously with other provisions in contract.
David Rayment and Andrew Smorchevsky represented the Respondent.
Reasons for the decision can be found here.